Dispute Avoidance in Construction Contracts Highlights

Dispute Avoidance in Construction Contracts: A Strategic Approach
Isabella Njeri

Introduction

In the construction industry, disputes are often seen as a natural by product of the complex relationships between clients, contractors, engineers, and other stakeholders. However, with proactive planning, careful contract management, and effective communication, many disputes can be avoided before they arise. The key to preventing conflicts lies not just in how disputes are resolved, but in how they are anticipated and minimized in the first place. We will explore strategies for dispute avoidance in construction contracts by focusing on proactive contract management, risk allocation, and the importance of clear communication and collaboration.

Proactive Contract Management: The Foundation for Dispute Prevention

Effective contract management is the first step in avoiding disputes. The way a contract is drafted, customized, and managed has a direct impact on how well potential issues are handled when they arise. One of the key areas to focus on is contract drafting. Often, disputes arise from ambiguous terms in the contract. It is crucial to use clear, plain language that leaves no room for interpretation. Standard contracts can be customized to fit specific projects, but care must be taken not to introduce ambiguity or confusion. For instance, the scope of work should be well defined, and deliverables should be clearly outlined. Terms like “as approved” in project specifications should be avoided as they can lead to disagreements about who is authorized to approve certain aspects of the work. Specificity ensures that both parties understand exactly what is expected.

In addition to clarity, risk allocation plays a central role in dispute prevention. Contracts should allocate risks to the parties best able to manage them. For example, design risks may be shared between the contractor and the architect, but the engineer must be involved when it comes to approval or rectification of designs. Financial capacity is another critical consideration many disputes stem from a lack of financial stability on the part of one of the parties. Often, the financial struggles of the employer can result in payment delays, which in turn can cause significant project delays. Ensuring that both parties are financially sound is key to maintaining smooth project progress.

Finally, performance bonds and guarantees should be carefully managed. For example, if a contractor is asked to extend a performance bond beyond the practical completion stage, it’s important to be clear about how this extension will be calculated, particularly if the completion timeline has not yet been determined. Misunderstandings in these areas can often lead to disputes.

The Importance of Risk Identification and Allocation

One of the fundamental causes of disputes on construction projects is the interpretation and allocation of risks. Construction projects are filled with uncertainties, including fluctuating weather, design flaws, material shortages, and labour issues. When risks are not clearly defined or allocated to the party best able to control them, misunderstandings often occur, leading to conflicts. Contract drafters should focus on allocating risks based on expertise. For example, the contractor may have some responsibility for design-related risks when producing shop drawings, but the ultimate responsibility for the design lies with the architect or engineer. Clear definitions of who assumes what risk will help eliminate disputes later.

Another critical aspect is financial capacity. While we often focus on the contractor’s ability to manage financial risk, we must also consider the employer’s financial capacity. If the employer faces financial difficulties, this can hinder the project’s progress and result in disputes, particularly around payment delays.

Effective Communication and Collaboration: A Key to Avoiding Disputes

Communication and collaboration are at the heart of successful project execution. A lack of effective communication is a leading cause of disputes, with stakeholders often misunderstanding each other’s expectations, requirements, or timelines. This lack of understanding can lead to delays, cost overruns, and even legal issues. To avoid these pitfalls, clear communication channels must be established from the beginning of the project. All stakeholders must understand how information will be shared, when progress updates will be provided, and how issues will be addressed. Having these channels in place reduces the likelihood of misunderstandings and allows parties to address potential conflicts early on.

In addition, collaboration between stakeholders is crucial. Collaboration should be driven by the best interests of the project, not individual agendas. When all parties are working toward the same goal, with open lines of communication, the chances of disputes arising are greatly reduced. Regular, documented updates are essential, as they provide a clear record of discussions and decisions, which can be referred back to if disagreements arise. Using modern tools like Building Information Modeling (BIM) can also greatly enhance communication and transparency. With BIM, stakeholders have real-time access to the same information, ensuring that everyone is on the same page regarding the project’s progress and requirements.

Poor communication and collaboration often lead to delays, cost overruns, and safety risks. In some cases, they may also damage reputations and create legal complications. Stakeholders must recognize that a failure to communicate effectively or work together can have serious consequences for the project as a whole. Transparency between all parties is essential to the success of a construction project. This includes clear and regular updates, documenting everything, and managing expectations. Failure to document decisions and updates makes it difficult to resolve disputes later. When all parties are kept informed, it’s easier to identify problems early and address them before they escalate into major issues.

The Role of Contract Review in Dispute Prevention

Even when using standard contracts, it is crucial to review the contract carefully before the project begins. Contract review helps identify any potential areas of ambiguity or imbalance in risk allocation that could lead to disputes. Customizing standard contracts should be done with a thorough understanding of the project’s unique needs and the potential risks involved. Regular site evaluations and stakeholder engagement are also important components of this review process. If one neglect to involve all relevant parties in the project’s planning and review stages, they may miss key issues that could cause disputes later on.

Conclusion: Making the Project’s Interests Supreme

As  discussed, avoiding disputes in construction contracts is a matter of proactive management, clear communication, and effective collaboration. However, at the heart of dispute avoidance lies a simple truth: the interests of the project must always come first. There’s an important lesson in the words of a consultant I often quote to my students: “There is no group of words in any language that can replace plain honesty between men and women, which will fully protect either of you if you plan to deceive each other.” This means that, while contracts are essential, they cannot replace mutual trust, transparency, and collaboration among stakeholders. If all parties prioritize the project’s success over individual interests and approach contract management with care and clarity, we can minimize the likelihood of disputes and set the foundation for a successful construction project.Let’s learn from each project, constantly improving our practices and ensuring that future projects are completed smoothly and without unnecessary conflicts.

Case Study on Dispute Avoidance in Construction: Lessons from the Field

Daniel Cherono

Introduction

The aspect of dispute avoidance topic that weighs heavily on the minds of professionals in the construction industry. On a daily basis, whether driving across the country or working on our own projects, we often come across stalled buildings, unfinished roads, or structures with defects. These are symptoms of problems that emerged during the construction phase but later manifest as disputes. Let’s be candid, disputes are a natural part of construction. While many of these issues never escalate into formal legal conflicts, they still create significant challenges for everyone in the industry. As architects, engineers, contractors, or employers, we are all involved in resolving and preventing disputes before they evolve into legal matters.

The Bigger Picture:

Let’s take a step back and consider the larger context. Construction projects are inherently unpredictable. The contracts are complex, and as we progress on-site, we quickly realize the magnitude of the challenges ahead. From the moment we break ground, there are countless uncertainties. We deal with multiple stakeholders, each with their own backgrounds, interests, and influences. These dynamics contribute to the technical complexity of the environment.

Projects, especially large-scale ones like skyscrapers or major infrastructure works, involve numerous stakeholders. Managing traffic, people, and resources is no easy task. Furthermore, the financial stakes are high, sometimes reaching billions of shillings, where even minor missteps can lead to disputes. And the consequences of unresolved disputes are not only financial but legal as well. This brings me to Lord Donaldson’s 1983 observation: “It is almost impossible to imagine a civil engineering contract of any substantial size that does not give rise to some form of dispute.” This statement doesn’t discredit the parties involved but highlights the intrinsic nature of the industry. What is critical, however, is how quickly and sensibly we can resolve these disputes to prevent their escalation.

Case Study:

Let’s delve into a case study that illustrates these challenges. I’ve seen numerous similar cases over the years and have tailored this one to highlight key lessons while avoiding the involvement of any specific parties. The case concerns the construction of an interchange between two major roads, N8 and N6, in a city. The project was valued at KSh 10 billion and had a 24-month timeline for completion.

The project was signed under the conditions of the FIDIC 2017 Red Book, but significant challenges quickly emerged, including delays in land acquisition and incomplete geotechnical investigations. The city authority had intended to complete land acquisition before the contract signing but failed to do so, leaving it to be handled during the construction phase. The project design was based on preliminary geotechnical investigations that did not fully account for certain underground conditions, meaning the city had to make provisions for further investigations during construction. Additionally, political pressures from the city governor to complete the project before elections complicated matters, leading to misaligned timelines and unrealistic expectations.

Upon starting the work, the contractor faced immediate challenges, including unacquired right-of-way, unforeseen obstacles, and the need for significant design changes, including redesigning the foundation to accommodate deep piles for the bridge. As a result, the contractor raised a claim for additional time and costs, requesting an extension and a cost adjustment of KSh 44 billion, approximately 40% of the original contract price.

These issues resulted in delays, disagreements over the scope of work, and disputes over costs and time extensions. Importantly, the dispute board, which is essential under the FIDIC conditions, was not appointed at the outset, causing further delays in resolving disputes in a timely manner. Eventually, the dispute board was formed, and its decision was binding. However, the employer declined to pay, leading to a court case and further legal complications. This case illustrates how delays in land acquisition, incomplete investigations, and poor communication led to avoidable conflicts and ultimately to project failure. The repercussions of such disputes are far-reaching: delays in project completion, escalation of costs, strained professional relationships and lengthy legal battles.

Key Questions and Takeaways:

Reflecting on this situation, we must ask: what could have been done differently? Were the contract terms clearly defined? Were risks properly allocated? Were project timelines realistic? How effective was communication between the parties involved?

One important takeaway is the critical need for early dispute resolution mechanisms. A properly appointed dispute board from the start could have helped prevent the escalation of these issues. Delaying key actions such as land acquisition and geotechnical investigations until after the project began was a costly mistake. We must also emphasize the importance of setting realistic timelines and ensuring clear and open communication throughout the project. Proactive dispute avoidance strategies, like early appointment of dispute boards, are essential in mitigating conflicts before they spiral.

Conclusion

In conclusion, we must resist the temptation to “kick the can down the road” and hope that issues will resolve themselves on their own. Disputes should be addressed promptly and efficiently, with a focus on resolution rather than escalation. As construction professionals, it is imperative that we embed dispute avoidance and resolution strategies throughout the entire project lifecycle.

Strengthening Dispute Avoidance in Construction: Insights from Mercy Okiro

Disputes in the construction sector can derail projects, increase costs, and create long-term legal battles. However, proactive measures such as clear regulations, quality assurance, and effective dispute resolution mechanisms can help prevent conflicts before they escalate. Mercy Okiro, a key figure in Kenya’s construction regulatory framework, provides a comprehensive overview of the National Construction Authority’s (NCA) role in shaping a more efficient and transparent industry. Mercy Okiro underscores the importance of NCA as a regulator, particularly in light of the historical issues with collapsing buildings in Kenya. She mentions the establishment of NCA as a response to these challenges, highlighting the authority’s mandate in coordinating industry development and advising the Cabinet Secretary on construction matters.

Regulating the Construction Sector

  1. Building Code 2024 and Sensitization Efforts: The new Building Code 2024, taking effect in March 2025, plays a critical role in improving standards and ensuring compliance. Okiro shares that NCA is actively engaging stakeholders, including consultants and the public, to ensure that industry players understand the changes and are prepared for the new regulations.
  2. Quality Assurance and Evaluation Criteria: One of the significant issues raised is the improvement of quality assurance mechanisms, particularly in how contractors and projects are evaluated. NCA is moving away from paper-based evaluations and planning to carry out physical inspections to ensure compliance with building standards and regulations.
  3. Dispute Resolution and ADR (Alternative Dispute Resolution): Okiro touched on the increasing importance of ADR mechanisms such as mediation, negotiation, and arbitration in resolving construction-related disputes. We need to enhance ADR capacity through training programs and partnerships with organizations like the Chartered Institute of Arbitrators and the Nairobi Center for International Arbitration. It will also be important to establish a dedicated construction dispute resolution body in Kenya, akin to structures in other countries like Canada, to streamline the resolution process and avoid delays.
  4. Insurance and Bonds:The importance of insurance, especially professional indemnity insurance for contractors and consultants was highlighted. NCA plans to issue guidelines around insurance and construction bonds to strengthen industry standards and mitigate risks.
  5. ICT and Technology Integration:Okiro advocates for the use of digital tools to improve project monitoring, compliance tracking, and dispute resolution. She stresses the importance of technology in improving efficiency, ensuring timely project completion, and reducing the costs associated with disputes.
  6. Empowering Stakeholders: stakeholder engagement and education through continuous workshops and training, especially on the new Building Code is important. NCA aims to empower all parties in the construction industry, thus reducing the likelihood of disputes.
  7. Proposals for Specialized Dispute Resolution Structures: In her final remarks, Okiro suggested the possibility of creating specialized courts or tribunals dedicated to construction matters. This would help address delays in dispute resolution and ensure that construction-related disputes are resolved more efficiently.

Mercy Okiro’s remarks reflect the importance of a multi-faceted approach to improving dispute resolution in the construction industry, focusing on regulation, quality assurance, stakeholder education, and enhanced ADR mechanisms. Her vision is cantered on ensuring a more efficient, transparent, and sustainable construction industry in Kenya. The discussion centers around several key issues related to construction contracts, dispute resolution, and the role of government in the context of construction projects, particularly those funded by donors. The primary focus is on the complexities of contract administration and how the practices diverge from what is theoretically intended.

Speakers’ Comments

Historically, after independence, many countries in East Africa began questioning the role of external engineers in their projects, leading to a shift in contract dynamics. The idea of an independent engineer, as envisioned in the FIDIC conditions of contract, was challenged. The employer often became entangled in the decision-making process, especially when financial interests were involved. In many cases, the engineer’s role was compromised, with employers exerting pressure to reject claims and avoid financial responsibility. This environment led to a tendency to dismiss legitimate claims, further complicating the resolution of disputes.

The challenge with donor-funded projects, which were the primary source of large-scale infrastructure in the region, is that they often had little room for negotiation or dispute resolution mechanisms. In these cases, engineers and consultants found themselves in a difficult position, where their professional advice was either ignored or overruled by employers who were more concerned with protecting financial interests. This dynamic led to a series of legal losses in arbitration cases, with the government and employers unable to defend their positions effectively.

The solution to these issues, as proposed by some of the speakers, lies in creating a more structured, transparent, and proactive approach to dispute resolution. One such mechanism is the Dispute Adjudication Board (DAB), which offers non-binding opinions on disputes. The DAB’s role is critical in avoiding disputes before they escalate, especially in large projects where communication breakdowns can lead to significant delays and financial losses. The importance of having qualified arbitrators and engineers involved from the outset is emphasized. These professionals should be part of the project team from day one, ensuring that any potential issues are flagged early and addressed promptly.

Another significant point raised is the need for dispute avoidance during project execution. Regular site meetings, where both parties can raise concerns, provide an opportunity to address issues before they escalate into formal claims. This proactive approach is seen as essential for preventing lengthy and costly legal battles, particularly when there are external factors such as material shortages or power rationing that could affect project timelines.

In summary, while the theoretical framework of construction contracts and dispute resolution is well-defined, local practices often fall short due to financial pressures, lack of independence, and a focus on short-term gains. The solution lies in adopting best practices from international standards, empowering engineers and arbitrators, and ensuring that dispute avoidance mechanisms are in place from the start. Through understanding the intent behind these systems and aligning practice with theory, the industry can move towards more effective and fairer contract administration, ensuring that all parties involved are held accountable and that disputes are resolved efficiently.